The intermediate connector of NASA’s first Area Release Formula Vehicle (SLS) was delivered to NASA in mid-July and is in transit to its launch site. The Launch Vehicle Stage Adapter (LVSA) ended through Teledyne Brown Engineering at the Marshall Space Flight Center (MSFC) in Alabama and officially moved to the company for use in the launch of Artemis 1, tentatively scheduled for 2021 expired.
In early July 17, the LVSA was deployed from its final integration site, Building 4649 in Marshall, to the agency’s Pegasus barge for the launch site. The tugboats moved the barge to the Mississippi River and south to the New Orleans area, where the barge stopped at the Michoud Assembly Facility (MAF).
“The LVSA left Marshall on the 17th, which was last Friday and is being transported on the Pegasus barge to KSC,” said Keith Higginbotham, NASA’s SLS program manager for the SLS program, on July 23. MAF just today and downloaded the hardware from some other article.
“They are unloading this and have also installed the spider encounter on the Pegasus, which will be transported with the LVSA to Cape Town. We have to get to Cape Town unless there are weather delays probably around August 2.”
(Note: A carrier removes the LVSA from building 4649 on the MSFC on July 17. The adapter transported on the Pegasus barge to be sent to the Kennedy Space Center launch site).
The lifting spider is a device of more than twenty tons that is fixed to the front end of the main steps to lift and rotate them horizontally to vertically and vice versa. It will be used in the KSC to pair the first Core Stage with SLS Rocket Boosters (SRB) next year.
The other booster spider has lately been attached to this first major level, as it is going through its Green Run verification crusade at the Stennis Space Center in Mississippi. In addition to the lifting spider, two of the self-propelled modular conveyors (SPMT) used to move the main steps outwards on its horizontal conveyor were also loaded onto the barge in MAF, the spider was fixed on one of them. The SPMT will eventually return with Pegasus to Mississippi to resume the base phase at the end of the Green Run crusade for delivery to KSC.
Following the switching of secondary gear to MAF, the barge was recovered by tugboats and was abandoned on 24 July. From New Orleans, the direction to the liberation site passes through the Gulf of Mexico, south and around the Florida Peninsula, and then north. east coast to Puerto Canaveral and, in spite of everything, to Turn Basin in KSC.
Upon arrival, NASA’s Exploration Ground Systems (EGS) program at KSC will get the LVSA for the eventual integration of the first SLS vehicle for launch in Artemis 1. The article will be stored in the Vehicle Assembly Building (VAB) until those activities begin. next year.
The timing of the launcher integration (also known as “stacking”) in Mobile Launcher-1 (ML-1) depends on when the Core Stage arrives at KSC. The SLS core will be the last major hardware detail to arrive at the launch of Artemis 1 and its delivery will feature the final touch of the ongoing Green Run tests.
For now, the LVSA will be parked in VaB’s High Bay 4, which is a transit domain for maximum SLS appliances before boarding the High Bay 3 integration mobile where ML-1 is installed. In the meantime, hands-on training will be conducted while the LVSA is in stock.
“We have more floor appliances like internal access platforms and a control bed,” said Allison Mjoen, NASA’s EGS operational allocation engineer. “We need to be able to continue to gain operational delight with technicians and engineers to use those platforms and some human tests will also be related to this.”
“These are the platforms we’ll install internally on LVSA once we’re stacked,” he said. “We’ll also make arrangements like this to make sure our team is in order once we enter our built-in operation.”
(LVSA image foot on the left was moved to building 4649 in MSFC for final integration paintings in June 2018. On the right, at the end of 2018, a breakable seal seal is lifted to attach it to the most sensitive adapter; the board will separate the ICPS from the top terrain of the LVSA at launch).
The LVSA is a component of the built-in spacecraft and payload detail (ISPE) of SLS Block 1; in equipment and shipping configurations, connects the main level to the floor of Block 1, the Intermediate Cryogenic Propulsion Stage (ICPS).
The adapter is mainly a structural interconnect connector, the rear is bolted to the front skirt of the Core Stage and the most sensitive part is connected to the ICPS hydrogen tank. Most of the upper stage, adding its unique RL-10B-2 engine and row nozzle extension, is closed through the launch and ascent of LVSA.
After the central stage main engine (MECO) is shut down, the LVSA remains with the core and the ICPS is separated from the most sensitive adapter. The adapter includes a separation formula and a breakable sealing gasket that is interspersed between the ICPS and the LVSA.
The breakable seal seal separates the top ground from the LVSA at the right time without generating debris from the explosive detonation.
The outside of the adapter is covered with a spray insulating foam (SOFI). In the case of LVSA, the foam thermally protects the adapter and its contents from heating in the declining atmosphere.
(Photo Pie: A NASA diagram showing the 3 parts of the spacecraft payload detail built into the SLS Block 1 Crew configuration; the adapters interleave the ground ICPS, with the LVSA connecting the main level below and the Orion level adapter (OSA) connecting the Orion spacecraft to the top).
Although the adapter is primarily structural, it also includes electric beams to join the Core Stage flight formula below with the LVSA separation formula, top-level flight computers and the Orion spacecraft and the equipment above. The vehicle is also covered with progression flight tools (DFI) for its first version and all those sensors are connected to Core Stage’s knowledge acquisition formula.
“ICPS will adapt to the LVSA volume, so it has a DFI that is connected to our adapter that runs up and down, so there’s a component,” Higginbotham said. “The other thing I would like to mention is that we will have some sets of internal cameras so that once the occasion of separation occurs, the ICPS continue its path and after its decomposition of the internal AVVI, there will be cameras that will capture this occasion as it happens.”
The two-level adapter cameras are among several mounts around the trigger that are stressed in the Camera Control Unit (CCU) in the Core Stage intermediate tank that will collect information about its launch and ascent. From a few seconds before MECO to several seconds later, the perspectives of LVSA cameras that capture ICPS separation will be transmitted by telemetry to the floor receiving stations.
There are also several circular access doors around the adapter circumference, which will be used in stacking operations in KSC. “Once we’re in a position to do the stacking [they] will allow us to pass through those platform access gates [when] we do mating,” Higginbotham said.
Teledyne Brown Engineering on the first LVSA keys for NASA
The Artemis 1 LVSA is the first flight unit produced through main contractor Teledyne Brown Engineering, but the time-built design for the program. The first unit is the fundamental welded arrangement used in a structural verification article for ISPE elements.
“The first one we built for the Structural Test Article (STA) was necessarily a monohest design that didn’t have all the orthogrille models and everything we did [for the flight unit],” Higginbotham said. “We take it to the maximum and restricted load, so we rate that the device will be able to fly with the needs it would have when it has other people on board.”
Restricted cargo is much one hundred percent of the estimated maximum flight. The final load is 140% of the maximum flight that the vehicle’s arrangement will have to bear to meet the protection of 1.4 for human qualification.
(Photo Pie: The LVSA welded for the first SLS launch moves to Building 4707 at THE MSFC in August 2017 for the application of its external spray foam coating).
The first soldered flight unit in the same place, the complex welding facility in Building 4755 in Marshall. The design is a conical cone consisting of 16 panels and a ring on the most sensitive and lower part. The panels were manufactured through AMRO Fabricating Corporation in California before being delivered to Teledyne Brown, founded in Huntsville, Alabama, near Marshall.
“All the plates were machined and manufactured there [at AMRO],” Higginbotham said. They go through an exclusive tycoon training procedure that they use to manufacture the panels for this structure.”
“They sent the panels to Teledyne where they were inserted and amenities and then transferred to Marshall.”
After welding, the completed design was transferred to Building 4707 at Marshall in August 2017 for the application of the Thermal Protection System (GST). Flight sets are treated with a primer to cover outdoor corrosion before spraying them with SOFI.
The LVSA moved to Building 4649 in Marshall in June 2018 for the latest integration activities in Great Bay.
“It ended up in Building 4707 where the GST was implemented and completed, and then it was transported to Building 4649 where we did the ultimate final integration work,” Higginbotham said. “So that’s where the FJA, the frangible gasket assembly, was installed, and then it took about 3 or 4 months to equip the rest of the pneumatic drive system, which is all aligned on the internal walls of the LVSA.
“We had this, we had the rest of the DFI sensor wiring that we had to install, we had the camera assemblies, and then the other vital thing, I would mention the acoustic covers that we had to put inside, which of the last things that were installed inside.
Higginbotham also noted that a hazardous fuel ventilation set and an Environmental Control Formula Ventilation (ECS) set were also installed as a definitive integration. As the liberator accumulates even as everything approaches, the article was officially transferred from Teledyne Brown to NASA to Marshall for release processing some time after delivery to KSC.
“We took the assets when it leaves 4649 and begins its adventure towards Cape Town, that’s when NASA takes over the team,” Higginbotham said.